Project :- Construction of Six laning of Chittoor-Thatchur (Andhra Pradesh)
Development of Six Lane Chittoor-Thatchur Highway from km 0.000 to km 43.800 on Hybrid Annuity Mode under Bharatmala Pariyojna in the state of Andhra Pradesh and Tamil Nadu (Package-I)
Client
Project Value
State
NHAI
1175.00 Crore
Andhra Pradesh
Project :- Construction of four-lane Greenfield Delhi-Amratsar-Katra Expressway Package-1 (Haryana)
Construction of four-lane Greenfield Delhi-Amratsar-Katra Expressway from Jussur Kheri on KMP Expressway to Junction with Rohtak-Panipat road (NH-709) near Rukhi Paani village (Km 0+000 to Km 34+000) on Hybrid Annuity Mode under Bharatmala Pariyojana in the State of Haryana (Pkg - 1).
Client
Project Value
State
NHAI
1130.58 Crore
Haryana
Project :- Construction of Six laning of Thuravoor-Paravoor section of New NH-66 (Old NH-47) on EPC Mode (Kerala)
Six Laning of Thuravoor (Design Ch. 378.612) - Paravoor (Design Ch. 417.000) sectrion of New NH-66 (Old NH-47) in the State of Kerala on EPC Mode under Bharatmala Pariyojana
Client
Project Value
State
NHAI
1118.00 Crore
Kerala
Project :- Construction of four-lane Greenfield Delhi-Amratsar-Katra Expressway Package-3 (Haryana)
Construction of four-lane Greenfield Delhi-Amratsar-Katra Expressway from Jind-Panipat Road (NH-352A) near Gangana Village to Junction with Jind Karnal Road (NH 709A) near Alewa Village (Km. 60+800 to 91+400) on Hybrid Annuity Mode under Bharatmala Pariyojana in the State of Haryana (Pkg-3).
Client
Project Value
State
NHAI
1040.07 Crore
Haryana
Project: Construction of Civil Works for HORC Project (Contract C6A) from New Patli to New Asaudha, (Haryana)
C6A design and Construction of Civil Works Earthwork, Bridges, Station other Works and Electrical Services from km 61500 to km 94000 bw New Patli to New Asaudha ,connectivity from Badsa to Sultanpur and Mandothi to Asaudha in the State of Haryana.
Client
Project Value
State
HORC
947.05 Crore
Haryana
Project :- 4-laning of Dhangaon-Boregaon section of NH-347BG & 753L (Indore to Boregaon-Pkg IV) (Madhya Pardesh)
4-laning of Dhangaon-Boregaon section of NH-347BG & 753L (Indore to Boregaon-Pkg IV) Design Ch. 81.000 to 139.000 (Length 58.000 Km) under Bharatmala Pariyojana Phase-I in the State of Madhya Pradesh on Hybrid Annuity Mode Project.
Client
Project Value
State
NHAI
806.66 Crore
Madhya Pradesh
Project :- Construction of 4-lane Bangalore-Chennai Expressway from Walajahpet to Arakkonam Section (Tamil Nadu)
Construction of 4-lane Bangalore-Chennai Expressway from Km 180.000 to Km 204.500 (Walajahpet to Arakkonam Section) in the State of Tamil Nadu under Bharatmala on Hybrid Annuity Mode (Phase-III/Package-II).
Client
Project Value
State
NHAI
779.74 Crore
Tamil Nadu
Project: Construction of Railway Doubling Work from Sitamarhi to Kundawa Chainpur, Bihar (39 Km), East Central Railway
Construction of doubling work including earth work, blanketing, minor bridges, major bridges, important bridge, track works, station & other buildings, platform work, LC work and other miscellaneous works for 25T Indian Railway Standard Loading from Sitamarhi (excl.)to KundawaChainpur (incl.) (i.e. Ch.106.500 to 145.500) (total39.00 km) in connection with doubling of Sitamarhi- Raxaul section in Samastipur Division of East Central Railway
Client
Project Value
State
ECR
671.47 Crore
Bihar
Project :- Improvement & Upgradation of NH-734 section of Moradabad - Thakurdwara - Kashipur in the state of Uttar Pradesh & Uttarakhand
Improvement & Upgradation of NH-734 section of Moradabad - Thakurdwara - Kashipur Including Moradabad & Kashipur bypasses on EPC basis in the state of Uttar Pradesh & Uttarakhand : "PackageI) Moradabad Bypass" (Length = 33.724 km), Start from Ch. 0+00 (Km. 144+381 of NH-24) and ends at Ch. 33+724 (Km 167+790 of NH-24)
Client
Project Value
State
NHAI
655 Crore
Uttar Pradesh
Project :- Akola to Khandwa GC Works) in the State of Madhya Pradesh of Nanded Division of South Central Railway Secunderabad
Construction (EPC) contract for ""(i) New Single Line from Ch: 652700m to Ch: 666200m (13.50 Km) and (ii) New Bidirectional/Double Line from Ch 666200m to Ch 669000m (2.80 Km) (including Usarni Yard) and Electrical General Services on Diversion Alignment from Ch: 652700m to Ch 669000m (16.30 Km) between Proposed Khaknar Kalan (Excluding) Station to Proposed Jamod Stations
Client
Project Value
State
SCR
568 Crore
Madhya Pradesh
Project :- Two lane with paved shoulder configuration with Parikrama Marg under EPC mode in the State of Uttar Pradesh
Improvement and up gradation from NH227B (84 Kosi Parikrama Marg) Package-V Design Km 140.960 (Patranga) to Km 160.200(Bahuvan Madar Majha) to two lane with paved shoulder configuration with Parikrama Marg under EPC mode in the State of Uttar Pradesh
Client
Project Value
State
MoRTH
529 Crore
Uttar Pradesh
Project: Railway Track Doubling Works from Darbhanga to Sitamarhi, Bihar – East Central Railway (ECR)
Construction of Formation (Earthwork & Blanketing), Bridges (Major & Minor), Retaining wall, Other Civil work ie. Gate Lodges, Goods Wharf, Service buildings, Passenger Platforms, Platform Shed, Circulating area, Road Work, Foot Over Bridge, Utility shifting etc. from Chainage 39.400 Km to Chainage-103.850 Km in connection with Doubling of Railway Track between Darbhanga and Sitamarhi Stations in Samastipur Division of East Central Railway
Client
Project Value
State
ECR
518.22 Crore
Bihar
HORC Railway Line – Civil Works and Electrical Services from Prithla to Dhulawat
New BG Double Railway Line of HORC project between stations Prithla and Dhulawat for: (i) Design and Construction of Civil Works (Earthwork, Bridges, Stations and Retaining Walls) from km -2.296 to km 12.00 & km 18.00 to km 20.842; (ii) Design, Supply, Installation, Testing & Commissioning of General Electrical Services from km -2.296 to km 12.00 and Km 18.00 to Km 20.842.
Client
Project Value
State
HORC
498.97 Crore
Haryana
Project :- Construction of Left out work of four Laning of Mahuva to Kagavadar Section of NH-8E (Gujarat)
Construction of Left out work of four Laning of Mahuva to Kagavadar Section of NH-8E from Km. 100.100 to Km 139.915 (Design Chainage from Km 100.450 to Km 140.470) (Package-III) in the state of Gujarat on Single Percentage Item Rate Basis.
Client
Project Value
State
NHAI
485.76 Crore
Gujarat
Project :- Improvement and up-gradation of newly declared National Highways NH-227B in the state of Uttar Pradesh on EPC basis.
Improvement and up-gradation of newly declared National Highways NH-227B(84 Kosi Parikrama Marg)Package II Design Km29.000 (Sarpur) to Km47.878/47.800 (Gosaiganj)in the state of Uttar Pradesh on Engineering, Procurement and Construction(EPC) basis.
Client
Project Value
State
MoRTH
444 Crore
Uttar Pradesh
Project :- Remodeling of Augmentation Canal from Hamida Head to Picholia Head (Haryana)
Remodeling of Augmentation Canal from Km 0 to 75.250 i.e. from Hamida Head to Picholia Head(Merging Point with WJC Main Branch)
Client
Project Value
State
WRD
380.18 Crore
Haryana
Project :- Resurfacing Of Runway And Allied Airfield Works At Air Force Station Tezpur (Assam)
Resurfacing Of Runway And Allied Airfield Works Including Area Drainage At Air Force Station Tezpur Under Ge I P Af Tezpur
Client
Project Value
State
MES
369.31 Crore
Assam
Project :- Construction of Elevated Corridor in Ranchi city (Jharkhand)
Construction of Elevated Corridor in Ranchi city from km 0.00 to km 3.570 of NH75 including down ramp on NH23 from km 0.000 to km 0.610 in the State of Jharkhand on EPC mode
Client
Project Value
State
NHAI
291 Crore
Jharkhand
Project :- Development of new greenfield airport at Bundi, Kota, Rajasthan
Development of new greenfield airport at Bundi, Kota, Rajasthan, for detailed designing, engineering, procurement and construction of airside works including earth works, grading, runway, apron, taxiways, isolation bay, civil and electrical works for NAV-AIDS facilities, perimeter road, approach road, operational and non-operational boundary wall, runway lighting system and allied works.
Client
Project Value
State
AAI
283 Crore
Rajasthan
Project :- Construction of advance landing ground and allied services at Nyoma Ladakh
Construction of advance landing ground and allied services for development of basic infrastructure at Nyoma Ladakh.
Client
Project Value
State
MES
218 Crore
Ladakh
Project :- Balance works of 4-laning of Rampur-Kathgodam (Uttar Pradesh)
Balance works of 4-laning of Rampur-Kathgodam section of NH-87 (New NH No. 09) from Km 0.000 (Km 190.000 of NH-24) to Km 42.791 (design Chainage Km 43.446) (Package-I) in the state of Uttar Pradesh on EPC Mode and Joint Venture with HRY Kundu Buildtech Pvt. Ltd.
Client
Project Value
State
NHAI
199.31 Crore
Uttar Pradesh
Project :- Construction and upgradation of road Joshimath bypass(Uttrakhand)
Construction and upgradation of road Joshimath bypass between Km 468 to Km 489 pt 350 design chainage 465 pt 150 to km 471 pt 500 under Chardham Pariyojana in Uttrakhand state Length 6 pt 35 Km
Client
Project Value
State
BRO
185.84 Crore
Uttrakhand
Project :- Execution of Earthwork in formation, Construction of Minor Bridges, Blanketing, P. Way linking works including supply of P-way fittings of NTPC Railway Siding, in Raigarh District, Chhattisgarh State (Package – IV A) (Chhattisgarh)
Execution of Earthwork in formation, Construction of Minor Bridges, Blanketing, P. Way linking works including supply of P-way fittings, Track ballast, PSC Sleeper and Points &Crossings in connection with construction of Railway Infrastructure from Kotarlia Station to 3/771 Km LP, Proposed CKRU, CKRD lines including Proposed CKR Station, ROR Section from Ch. 1/00Km. to 6/449 Km except ROR portion and 100 metre approach bank on either side, Both Y-conn. (North and south) and Kotarlia Station to 13/280 Km TM of NTPC Railway Siding, in Raigarh District, Chhattisgarh State (Package – IV A).
Client
Project Value
State
RITES
179.06 Crore
Chhattisgarh
Project :- Construction of Earthwork, Bridges, Station Buildings, Retaining Walls and other misc
Construction of Earthwork, Bridges, Station Buildings, Retaining Walls and other misc. Works in c/w laying of New BG Double Railway line of HORC Project from Km 49.7 to Km 55.6 and its connectivity from proposed Manesar STN to existing Patli STN.
Client
Project Value
State
HRIDCL
158.17 Crore
Haryana
Project :- Construction of Flyoverv City Bharatpur On EPC Mode
Construction of Flyover from Kali Bagichi Chouraha to RBM Hospital via Bijlighar Chouraha in Bharatpur City Bharatpur On EPC Mode
Client
Project Value
State
PWD-RAJASTHAN-JAIPUR
131 Crore
RAJASTHAN
Project :- Extension of Ashram Flyover to DND Flyover (SH: FOBs, Ramps, Footpath road) (Delhi)
Extension of Ashram Flyover to DND Flyover (SH: FOBs, Ramps, Footpath road work including road sinage, streetlight works, drainage & allied works).
Client
Project Value
State
PWD-NCT of Delhi
128.79 Crore
Delhi
Project :- Development of Infra. facilities Industrial Estate Dharuhera, Distt Rewari Haryana
Development of Infra. facilities including trial run for 3 months, DLP of 36 months and 12 months of O and M of all infrastructure during first year of DLP on turnkey basis at Sector 15, 16 and 17 Industrial Estate Dharuhera, Distt Rewari Haryana
Client
Project Value
State
HSIIDCL
64.23 Crore
Haryana
Project :- Stabilization of land slide and slope protection on Gangotri – Dharasu-Rishikesh road (NH34) on EPC mode in the State of Uttarakhand.
Stabilization of land slide and slope protection at Km 38.375 to Km 38.515 Km 45.790 to Km 46.100 Km 68.280 to Km 68.400 Km 69.320 to Km 69.430 Km 84.940 to Km 85.050 Km 106.030 to Km 106.460 Km 108.045 to Km 108.310 Km 117.430 to Km 117.550 on Gangotri – Dharasu-Rishikesh road (NH34) on EPC mode in the State of Uttarakhand. (nos of land slide – 08 nos)”
Client
Project Value
State
BRO
51.81 Crore
Uttarakhand
Project:- Treatment of 01 nos. of landslide location (Dabarkot) under EPC mode in the state of Uttarakhand
Treatment of 01 nos. of landslide location at Ch. 79.850 to 80.300 (Dabarkot) on NH-134 under EPC mode in the state of Uttarakhand.
Client
Project Value
State
PWD-DEHRADUN
34 Crore
Uttarakhand
Project:- Special Protection Work on Rehabilitation and Restoration of Sinking Sliding Zone from Km 70 to Km 71 with JICA TS (Sikkim)
Special Protection Work on Rehabilitation and restoration of Sinking Sliding Zone from Km 70 to Km 71 with JICA Technical Assisstance including widening of Narrow in the state of Sikkim.
Client
Project Value
State
NHIDCL
33.85 Crore
Sikkim
Project:- Treatment of landslide zone 11 location from km 101.01 to km 191.365 on NH-125 (New NH-09) in the State of Uttrakhand
Treatment of landslide zone 11 location from km 101.01 to km 191.365 on NH-125 (New NH-09) in the State of Uttrakhand under EPC mode
Client
Project Value
State
PWD Uttrakhand
18.70 Crore
Uttrakhand